How much sun does Barrie actually get?

The yearly average for equivalent full sunlight hours in Barrie is estimated at around 2,000 hours, similar to Peterborough, which has roughly 296 days with some sunshine. Total sunshine hours for Barrie come to about 2,510 a year. (Source: climate-data.org.)

How many panels does a 6 or 8 kW system need?

Assuming 500-watt panels, a 6 kW system is about 12 panels and an 8 kW system about 16.

What about snow on the panels?

Leave it. Do not try to brush or clean the panels off. Snow guards can be fitted to help manage build-up, and a system designed with our annual snowfall in mind will give you a realistic production estimate. Summer output generally offsets the low production of the snowy months.


Net metering and energy plans

Does Alectra support net metering?

Yes. Under Ontario’s net metering initiative you can send surplus energy back to the grid and receive credits on your electricity bill.

Can I stay on the Ultra Low Overnight plan with net metering, or must I switch to Tiered?

You can stay on a time-of-use plan and participate in net metering. The Ontario Energy Board confirmed this in a bulletin issued on 17 January 2023.

Is there still a cap on how many homes can send power to the grid?

Ontario regulations allow households to take part in net metering with a system of 10 kW or less. Changes in 2022 also opened up third-party ownership arrangements such as leases and power purchase agreements. Hydro One’s net metering page and the IESO site have the detail.

Which is better value in Barrie: load shifting on the Ultra Low Overnight plan, or net metering?

Net metering is usually the bigger benefit, because generating your own power effectively locks in your rate for up to 30 years. With a rate plan, however low the rate, you are still paying whatever the utility charges and will charge in future.


Installation and permits

What permits do I need in Barrie?

Grid-tied solar: yes, a building permit is required. You will need to submit detailed plans covering structure and electrical work. The review looks at whether your roof can carry the array, at electrical safety, and at compliance with local codes and the Ontario Building Code. You also have to coordinate with your utility to connect to the grid, under the Ontario Energy Board’s rules.

Grid-tied battery storage: yes, also a permit, so the system is safely integrated with your electrical service. Similar process, similar detail.

Both together, with or without net metering: permits are needed either way, and net metering does not usually change the basic permit requirements. It does add paperwork: you will need the utility’s approval of your net metering agreement so that billing and credits work correctly.

(See the City of Barrie’s page on solar installation.)

How long does installation take?

  • Smaller systems (4 to 5 kW): one day.
  • Average systems (7 to 10 kW): one to two days.
  • Larger systems (12 to 18 kW): two to four days.

If the site is pre-wired, one to two days. If not, three to four. Solar is often installed first and the batteries added later as they arrive. Net metering runs on its own timeline and varies by region: there are two applications, one before installation and one after the install and inspection reports are passed.

Should I replace the roof first?

If the roof is near the end of its life, yes. A solar system lasts 30 years or more, so replacing the roof beforehand saves money later.

What does it cost to remove and refit panels for a roof replacement?

Typically 10 to 15% of the original installation cost.


Technical questions

Trees shade part of our south-facing roof. Will panels still work?

It depends on how much shade and when. Proper design and assessment, taking tree heights and shading patterns into account, is what tells you. Get a site-specific evaluation from an installer.

Can I charge a battery overnight on the cheap rate and use it at peak?

Yes. That is load shifting, and it is one of the main benefits of pairing solar with battery storage. On the Ultra Low Overnight plan the peak period runs from 4 p.m. to 9 p.m., and a battery charged by solar and by the off-peak rate can carry you through it.

Micro-inverters or optimizers with a Tesla Powerwall?

Optimizers, because they reduce the number of DC to AC to DC conversions and so improve efficiency. The Powerwall 3 also addresses this. Note that Powerwalls can take six months to a year to arrive.

When the grid goes down, do grid-tied panels stop producing?

Yes, and deliberately. It is a safety feature that prevents your system feeding power into a dead grid, which could endanger utility workers during an outage. If you have batteries, they take over and keep your house running.


Further reading

  • EnergyHub — Ontario-specific guidance on solar and net metering.
  • Search YouTube for step-by-step builds of a 5.6 kW grid-tied system if you want to see the work involved.
  • Power Down, our August climate action.